Current Engineering Work Load

41

Active Projects

4

Engineers Carrying Work

6

Sales People Represented

28

Projects with Contract

Projects by Sales Person

Contract Mix

Projects by Engineer

Active Project List

3524 & 3525
San Diego Police Department
Project Engineer: Xiaohan
Contract Sales Person: Francis Tenggardjaja
Start Date
2026-04-17
Projected End
2026-05-29
Added
2026-05-28
Status
Contract
3525 (older existing NS machine) - 1. 208V. Working on the drawing now.
3524 (newer existing NS machine) - 1. 480V.  2. The existing reclaim tank is mounted on a concrete platform with seismic restraint. For the new RO tank, add seismic restraint? 
3091
New Haven Train Wash
Project Engineer: Behrad
Contract Sales Person: David Newell
Start Date
2026-05-26
Projected End
2026-12-12
Added
2026-05-28
Status
Contract
Reviewing the Spec. and contract drawings. Issued 6 RFIs on 5/27/2026 and emailed them to David for customer responses. Requested CAD drawings and train profiles from David on 5/20/2026, no information is received as of 5/28/2026. Communicating with a new display supplier to find out if their display product can be used on this new project.
3493
Enterprise Conyers
Project Engineer: Kash
No Contract Sales Person: Victor Sanchez
Start Date
2026-05-27
Projected End
2026-05-28
Added
2026-05-28
Status
No Contract
Drawings complete, need to be released.
3522
JD's Truck Wash
Project Engineer: Kash
No Contract Sales Person: Brad Quay
Start Date
2026-05-26
Projected End
2026-07-03
Added
2026-05-28
Status
No Contract
Truck wash drawings to be prepared from Ceccato's shop drawings.
3372
Azer Arco
Project Engineer: Kash
Contract Sales Person: Max Diaz
Start Date
2026-05-27
Projected End
2026-06-05
Added
2026-05-28
Status
Contract
Drawings in progress.
3474
Palm Tran South
Project Engineer: Behrad
No Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-23
Status
No Contract
50% design and completed on 4/16/26 and emailed to Francis and David
3170
Fallbrook Drive Metro Houston
Project Engineer: Shawn
No Contract Sales Person: Michael Howlett
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-23
Status
No Contract
No update
3158
Gananda CSD
Project Engineer: Shawn
Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-23
Status
Contract
"Drawings (Rev -) have been released 03.26.26.
OM?"
XXXX
N/S Permit
Project Engineer: Behrad
Contract Sales Person: Francis Tenggardjaja
Start Date
2024-01-31
Projected End
2026-09-30
Added
2026-04-16
Status
Contract

Q3 provide the updated structural drawings for Epic and Q3. Both are reviewed and comments are emailed back to Q3 for corrections.

Epic finally provided post to beam connection calculations and it will be included in the final submittal.

Per Epic, the required details for the (3) remaining comments on plans S3.1 and S3.2 should be supplied by either Kabtech or Q3. Behrad emailed Q3 to find out if those details can be provided by Q3.

When the final details are provided by Q3, they need to send the final seismic drawings to Epic for PE stamp.


Industrial waste requested data sheet for the waterjet and 3-stage clarifier and all the data sheets were submitted on 5/7/2026.

Received final approval from Industrial Waste on 5/13/2026 and uploaded the agency clearance to the city’s portal the same day.

Q3 provided ADA-Compliant restroom drawings and requested some extra dimensions on 5/4/2026. Requested measurements were email back to Q3 on 5/5/2026. Per Q3, some modifications to the restrooms such as partition relocation, handrail addition and sinks change will be required.

Epic reviewed Q3’s structural drawings and confirmed they are good. However, upon reviewing the structural drawings, Behrad found out that there are still (4) items that need to be addressed by Epic. The request to Epic was sent on 5/13/2026 and followed up again on 5/20/2026.

Epic responded to some of the structural questions and updated the square shape platform calculations.

Behrad completed all the responses to the city comments. Just waiting on Epic to send the final information to enable Q3 put the submittal together.


Paint Booth inspection is passed and permit is issued. A copy of the permit is emailed to the inspector. Another copy is emailed to Q3 to be included in the submittal. The original copy is given to Alex.

Q3 engineer inspected the building on 4/28/26 and provided the requested submittal for Industrial Waste the same day. Submittal will be emailed to Industrial Waste on 4/28/26.

Revised electrical plans are prepared by NAI and emailed to Q3 to be included in the final submittal.

Revised seismic calcs. for both platforms are provided by Epic and emailed to Q3 to be included in the submittal.

Epic Structural initial Observation form is emailed to Q3 to be included in the final submittal. The issuance of final structural observation form by Epic is pending until NS changes all the base plates after receiving the city approval on the plans.

Q3 provided the structural drawings for Epic. Epic needs to review these drawings and make the necessary comments. Drawings are emailed to Epic on 4/28/26.

Q3 provided responses to the city’s structural comments. Behrad is going to review the responses and finalize them.

Q3 provided structural calcs. for the slab. Calculations will be included in the final submittal.

Q3 provided the structural observation form for the Paint Booth. Form will be included in the final submittal.


Paint Booth Inspection is scheduled for 4/24/2026.

Francis and Q3 agreed on the extra cost for Paint Booth  Structural Observation and restroom as-built on 4/21/26.

Paint booth photos & restroom as-builts were prepared and emailed to Q3.

Platforms photos were prepared & emailed to Epic for structural observation. Greg provided the initial Structural observation form, however, the final form for inspection cannot be provided until base plates are changed.

Emailed the Structural observation to Q3 to add to the revised submittal.

Requested Epic to work on the platforms structural calcs. and revised the plans and submit ASAP.

There is no access to restroom ceilings and the drainage as-built cannot be provided by NS.

Requested Q3 to provide proposal for providing code compliance drainage plans for the building to be submitted to industrial waste.

Q3 proposal is approved by Francis and NS has requested Q3 to schedule a site survey to prepare the plans.


Q3 has performed the initial evaluation and recommended 22"x22" base plates for both platforms.
Epic is working on revising the calcs based on the recommended base plates
Q3 has sent the new fee schedule for new slab calcs and (1)structural observation (fees need to be discussed)
Epic can perform Structural observations if NS provides photos of the platforms.
Q3 needs NS to provide as-builts of the restrooms
NS contacted City of LA, County of LA, City of Santa Clarita and Public record. No agency has building plumbing record
NS has received approval on Paint booth plans. Fee is paid. Permit will be issued after inspection. Inspection is requested and followed up on 4/9/26.

N/A - 2
SEPTA train wash
Project Engineer: Shawn
No Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
No Contract
continues to support, submitted on basic equipment layout
N/A - 1
GCRTA
Project Engineer: Shawn
No Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
No Contract
Completed the basic equipment layout for bid.
N/A
Canarsie, 20th Street, Jamaica Yards
Project Engineer: Shawn
No Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
No Contract
Currently, working on the tanks design.
3241
Columbia Solid Waste
Project Engineer: Xiaohan
Contract Sales Person: David Newell
Start Date
2026-01-05
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Response and VFD datasheet were submitted on 5/26/26.
3461
MV Transportation Atlantic Ave
Project Engineer: Behrad
Contract Sales Person: Michael Howlett
Start Date
2026-02-19
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Drawings and submittal are completed and submitted for review. Waiting on approval.
3414
Beaver County Bus Wash
Project Engineer: Kash
Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Submittal needs to be revised. 
3412
CATS Transit - Anderson, IN
Project Engineer: Xiaohan
Contract Sales Person: David Newell
Start Date
2026-01-26
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Drawing were released. Will work on O&M;.
3388
Houston Metro Train ROC
Project Engineer: Xiaohan
Contract Sales Person: Michael Howlett
Start Date
2026-02-26
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
The proposed drawing package was submitted on 5/13/26. 
3350
LAMTA Div 22
Project Engineer: Behrad
Contract Sales Person: Francis Tenggardjaja
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Shop drawings and submittal are completed and emailed to Francis on 4/15/26. Jorge has completed the air blower frame model and it is sent to Behrad for review.
3245
Harris County Bus Wash
Project Engineer: Kash
Contract Sales Person: Michael Howlett
Start Date
2026-04-01
Projected End
2026-06-30
Added
2026-04-16
Status
Contract
Drawings complete and sent out. Pending approval
3244
WCTA Freedom Transit
Project Engineer: Shawn
Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
No Update
3240
Thomas School GA
Project Engineer: Behrad
No Contract Sales Person: David Newell
Start Date
2025-08-28
Projected End
2026-04-30
Added
2026-04-16
Status
No Contract
No Update. Drawing is done and sent to David.
3178
North Kansas City Schools Transport center
Project Engineer: Xiaohan
Contract Sales Person: David Newell
Start Date
2025-12-11
Projected End
2026-04-30
Added
2026-04-16
Status
Contract

Will work on O&M.
3143
Madison County Transit
Project Engineer: Behrad
Contract Sales Person: David Newell
Start Date
2025-09-22
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
4M manual is supplied to the customer.
3139
Gray Line Tennessee
Project Engineer: Xiaohan
Contract Sales Person: David Newell
Start Date
2025-09-19
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Will work on O&M;.
3100
Burnt Hills Ballston Lake
Project Engineer: Shawn
No Contract Sales Person: David Newell
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
No Contract
No update
3032
DOA Las Vegas
Project Engineer: Kash
Contract Sales Person: Francis Tenggardjaja
Start Date
2025-03-16
Projected End
2027-11-30
Added
2026-04-16
Status
Contract
Drawings need to updated to match the architectural design changes
3019
Wabash Ave Metro Rail Yard
Project Engineer: Shawn
Contract Sales Person: David Newell
Start Date
2025-05-09
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
No update
3017
White Earth Transit
Project Engineer: Shawn
Contract Sales Person: David Newell
Start Date
2025-05-02
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
need an OM
2973
LAUSD Sun Valley
Project Engineer: Kash
No Contract Sales Person: Michael Howlett
Start Date
2026-02-11
Projected End
2026-06-30
Added
2026-04-16
Status
No Contract
Site visit done, electrical scope needs to be clarified.
2935
R.E.A.L Multi Modal Transit Facilty
Project Engineer: Behrad
Contract Sales Person: Michael Howlett
Start Date
2025-07-10
Projected End
2026-04-30
Added
2026-04-16
Status
Contract

Drawings are released for production. Production team needs to make a new 12' 4M frame since the frame they made based on the job order was wrong and it was 14'.
2921
City of Clearwater - Tampa, FL
Project Engineer: Shawn
No Contract Sales Person: David Newell
Start Date
2024-08-29
Projected End
2026-04-30
Added
2026-04-16
Status
No Contract
No update. Per David, bid will be out in Nov. / Dec.
2830
San Bernardino Detention Center
Project Engineer: Kash
No Contract Sales Person: Michael Howlett
Start Date
2025-12-15
Projected End
2026-06-30
Added
2026-04-16
Status
No Contract
Scope delineation is progress. 
2743
West Metro Houston
Project Engineer: Shawn
Contract Sales Person: Michael Howlett
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Need an OM manual
2741
City of Torrance
Project Engineer: Kash
Contract Sales Person: Michael Howlett
Start Date
2025-11-18
Projected End
2026-06-30
Added
2026-04-16
Status
Contract
Permit application is approved. NS is in process of obtaining the Pocket License from the City. 
2689
MBTA Quincy
Project Engineer: Xiaohan
Contract Sales Person: Francis Tenggardjaja
Start Date
2024-03-17
Projected End
2026-04-30
Added
2026-04-16
Status
Contract

HMI submittal sent on 4/27. Will work on O&M once all equipment is shipped.
2632
Train Wet Test - Siemens
Project Engineer: Behrad
Contract Sales Person: Francis Tenggardjaja
Start Date
2024-04-09
Projected End
2026-04-30
Added
2026-04-16
Status
Contract

Spare part list was supplied to the customer. Arturo is working with Ebry on the program.

Conference
call with Siemens happened on 4/27/26. Siemens requested the following items:
1- Override Function for low Temp. 2- New flow meter calibration 3- No
Over-pressure protection 4- Remove four extra pressure sensors 5- Make the
PLC calculations functional 6- Spare part list for small items.

Javier needs to coordinate with Ebry for the PLC programming.
2448
New Jamaica, NYCT(Bus Wash)
Project Engineer: Shawn
Contract Sales Person: Francis Tenggardjaja
Start Date
2023-05-26
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
No update on the submitted the testing procedure on 02.25.26
need to work on OM manual.
2429
LA DOT Sylmar
Project Engineer: Behrad
Contract Sales Person: Michael Howlett
Start Date
2026-04-01
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Waiting on Michael to schedule a site visit.
2135
MOA Alaska
Project Engineer: Behrad
Contract Sales Person: Michael Howlett
Start Date
2025-12-05
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Plans are completed and sent to customer for review. Architect has incorporated NS plans into their 60% submittal. This is not a job yet.
3092
Palm Trans Bus Wash
Project Engineer: Behrad
No Contract Sales Person: David Newell
Start Date
2025-05-27
Projected End
2026-04-30
Added
2026-04-16
Status
No Contract
Revision #4 is issued on 5/28. Changed the Qty. of the blowers, changed the blowers to 7.5HP, added (2) undercarriage washes, updated the equipment layout, plumbing and electrical layouts. Updated the power table to stay within the 180A power limit. 
1126
OC Streetcar Train Wash
Project Engineer: Behrad
Contract Sales Person: Michael Howlett
Start Date
2019-03-11
Projected End
2026-04-30
Added
2026-04-16
Status
Contract
Speed display issue has remained unsolved. Xiaohan is working with a factory in China to find out if they can fix the electronic board.
No projects match that Project Engineer filter.